Firuzkoy Wastewater Tunnel

  • Client : Istanbul Metropolitian Municipality
  • Location : Istanbul / TURKEY
  • Scope of Work :
    • Tunnel construction with TBM (Tunnel Boring Machine) having Ø2600mm. internal diameter,pre-cast segmental lining as 1st and reinforced concrete lining as 2nd layer,
    • Total length of tunnel between start and end points is 3.770 meters,
    • 5 tunnel shaft construction,
    • Branch tunnel construction of Ø1800/1200 mm. internal diameter and 300 meter long
    • Construction of wastewater collectors of Ø3600 mm. diameter and 1160 meter long.
  • Start Date : 01.12.2008
  • Finish Date : 15.12.2011