East Blacksea Natural Gas Pipeline Phase-3
- Client : Botas Petroleum Pipeline Corporation
- Location : Bayburt - Rize / TURKEY
- Scope of Work : Construction, installation and commissioning of ~115 kms 16” dia. Natural gas intercity distribution pipeline from Bayburt to Rize.
Besides the main pipeline, below items are realised:
- 3 ea 16’’ line valves,
- 1 ea 16’’ pig receiving station,
- 1 ea 16’’ take-off valve,
- 1 ea 8’’ take-off valve,
- Excavation & backfilling of 115 kms, 16’’ dia., pipeline, Railway, highway and river crossings through the line via micro-tunnelling method,
- NDT tests, hydraulic pressure tests and cathodic protection
- Start Date : 01.06.2005
- Finish Date : 01.02.2008