East Blacksea Natural Gas Pipeline Phase-3

  • Client : Botas Petroleum Pipeline Corporation
  • Location : Bayburt - Rize / TURKEY
  • Scope of Work : Construction, installation and commissioning of ~115 kms 16” dia. Natural gas intercity distribution pipeline from Bayburt to Rize.

    Besides the main pipeline, below items are realised:
    • 3 ea 16’’ line valves,
    • 1 ea 16’’ pig receiving station,
    • 1 ea 16’’ take-off valve,
    • 1 ea 8’’ take-off valve,
    •  Excavation & backfilling of 115 kms, 16’’ dia., pipeline, Railway, highway and river crossings through the line via micro-tunnelling method,
    • NDT tests, hydraulic pressure tests and cathodic protection
  • Start Date : 01.06.2005
  • Finish Date : 01.02.2008