Corum Natural Gas Compressor Station
- Client : Botas Petroleum Pipeline Corporation
- Location : Corum / TURKEY
- Scope of Work : Design, material supply,construction, installation and commissioning works of three units of compressors with total 45,9 MW installed power, pig station, station main input-output lines with 48’’ diameter, recycle linewith 24’’ diameter, unit input-output lines, input output anti-surge lines of separator filters, input output lines of gas cooler with 16’’ diameter and Scada connection in the form of 2+1 configuration as gas turbine + compressor package (2 unit in operation, 1 unit backup).
- Start Date : 21.05.2007
- Finish Date : 26.06.2008