Abu Zayyan - El Ruhebat Water Supply Project

  • Client : Man Made River Authority ( MMRA )
  • Consultant : IBK(Avusturya) - LTC(Libya) - PHS(Avusturya) JV
  • Designer : Halcrow UK
  • Location : Gharyan / Libya
  • Scope of Work : The project is a design and build project with the purpose of supplying potable and irrigation water to Jebel Al Gharbi area near Tripoli City. The main line is GRP pipe with a length of 120 km. The diameter of pipes are between 800-2400 mm. The project supplies water to 10 towns and 38 villages. There are 2 water storage tanks, one 27.000 m³ capacity and the other 13.000 m³ capacity. There is also automation in the whole system.
  • Start Date : 08.06.2006
  • Finish Date : 10.11.2010